| curl release procedure - how to do a release |
| ============================================ |
| |
| in the source code repo |
| ----------------------- |
| |
| - edit `RELEASE-NOTES` to be accurate |
| |
| - update `docs/THANKS` |
| |
| - make sure all relevant changes are committed on the master branch |
| |
| - tag the git repo in this style: `git tag -a curl-7_34_0`. -a annotates the |
| tag and we use underscores instead of dots in the version number. |
| |
| - run "./maketgz 7.34.0" to build the release tarballs. It is important that |
| you run this on a machine with the correct set of autotools etc installed |
| as this is what then will be shipped and used by most users on *nix like |
| systems. |
| |
| - push the git commits and the new tag |
| |
| - gpg sign the 4 tarballs as maketgz suggests |
| |
| - upload the 8 resulting files to the primary download directory |
| |
| in the curl-www repo |
| -------------------- |
| |
| - edit `Makefile` (version number and date), |
| |
| - edit `_newslog.html` (announce the new release) and |
| |
| - edit `_changes.html` (insert changes+bugfixes from RELEASE-NOTES) |
| |
| - commit all local changes |
| |
| - tag the repo with the same tag as used for the source repo |
| |
| - make sure all relevant changes are committed and pushed on the master branch |
| |
| (the web site then updates its contents automatically) |
| |
| inform |
| ------ |
| |
| - send an email to curl-users, curl-announce and curl-library. Insert the |
| RELEASE-NOTES into the mail. |
| |
| celebrate |
| --------- |
| |
| - suitable beverage intake is encouraged for the festivities |
| |
| curl release scheduling |
| ======================= |
| |
| Basics |
| ------ |
| |
| We do releases every 8 weeks on Wednesdays. If critical problems arise, we can |
| insert releases outside of the schedule or we can move the release date - but |
| this is very rare. |
| |
| Each 8 week release cycle is split in two 4-week periods. |
| |
| - During the first 4 weeks after a release, we allow new features and changes |
| to curl and libcurl. If we accept any such changes, we bump the minor number |
| used for the next release. |
| |
| - During the second 4-week period we do not merge any features or changes, we |
| then only focus on fixing bugs and polishing things to make a solid coming |
| release. |
| |
| Coming dates |
| ------------ |
| |
| Based on the description above, here are some planned release dates (at the |
| time of this writing): |
| |
| - June 17, 2015 (version 7.43.0) |
| - August 12, 2015 |
| - October 7, 2015 |
| - December 2, 2015 |
| - January 27, 2016 |
| - March 23, 2016 |
| - May 18, 2016 |
| - July 13, 2016 |
| - September 7, 2016 |